Nickle contracting, LLC was the General Contractor for all projects, earthwork, excavation, concrete, post tension basketball court, post tension multi-purpose court, shade structures, turf, irrigation, site lighting, decorative fencing, seat walls, and decorative landscaping. Nickle Contractin, LLC performed 75% of the work with its own forces. Arbuckle Park is another Job Order Contract that was done for the city of chandler.
CONSTRUCTION DATE:
MAY 2007 - NOVEMBER 2007
ORIGINAL CONTRACT:
$1,218,205.00
FINAL CONTRACT:
$1,255,725.00
NOTE: Owner: City of Chandler
Mike Ohland, Park Planning Superintendent
602.782.2743
Don Tolle, Contract Administration, Park Dept.
602.462.1425